UPGRADING & EXPANDING OF OOREEDOO EXISTING DATA CENTER DE ORAN ET OFY
TECHNIPROJET participated in the technical studies of the project of increasing the IT capacity of 3 Data Centers from 160 KW to 550 KW whilst migrating from a Tier 1 architecture to a Tier 3 architecture without service interruption.
Project Details
Project Owner: Ooredoo
Calendar: 2018-2019
Mission : Electrical execution studies
Budget : 3,8M €